Funding cut for US nuclear waste dump

Yucca Mountain's end would leave the country with few alternatives for a long-term repository.

Billions of dollars spent on the proposed Yucca Mountain repository could be wasted.Billions of dollars spent on the proposed Yucca Mountain repository could be wasted.US DEPARTMENT OF ENERGY/SPL

Some ten billion dollars and two decades into the project, the proposed US nuclear waste dump at Nevada's Yucca Mountain has hit a major and possibly decisive stumbling block: President Barack Obama has proposed eliminating all funding for scientific research on the deep-rock repository, 140 kilometres northwest of Las Vegas. As Yucca Mountain has been the United States' only potential long-term repository since 1987, the decision once again raises the issue of what to do with the country's high-level nuclear waste.

In his budget for fiscal year 2009, to be released in early May, Obama is expected to propose spending only the estimated US$40 million needed to let the Nuclear Regulatory Commission (NRC) move forwards in evaluating the licence application for Yucca Mountain. The licence request, filed last June under George W. Bush's administration, requires the NRC to investigate the site's technical suitability, a process expected to take three to four years.

But the new administration says it will halt the controversial project regardless of the licence ruling, saying that the country can find another solution for long-term management of its nuclear waste. "I think we can do better," energy secretary Steven Chu told the Senate committee on energy and natural resources in March. The Department of Energy has established a commission to explore alternatives, which could report back within a year.

For now, high-level waste remains in cooling ponds and dry-cask storage containers at the country's 104 nuclear power plants. But that is a short-term and expensive solution: since the government missed a 1998 deadline for opening the Yucca Mountain facility, it has been paying fees to the power plants, a bill that could rise to $11 billion by 2017. Some states have threatened to stop contributing unless an alternative to Yucca Mountain is found.

Tom Kauffman, a spokesman for the industry policy group the Nuclear Energy Institute, says that waste can be safely stored on-site "indefinitely" while a long-term solution is found, but others say an answer is needed. "I live in a state with three [nuclear] power plants," says Michael Corradini, a nuclear engineer at the University of Wisconsin in Madison. "It's very unsatisfying to not have a complete, thought-out process."

Source: OCRWM

One possibility is to begin searching for another geologic repository. Yucca Mountain's capacity was to be legally capped at 70,000 tonnes of nuclear waste, even though it could technically hold 4–9 times that amount, so the US government had intended to open a second site, says Charles McCombie, a nuclear-waste consultant based in Gipf-Oberfrick, Switzerland. "It would be sensible for the United States to begin looking at another repository-siting programme, whether or not Yucca Mountain shapes up," he says.

But the government has spent decades studying Yucca Mountain as the only potential site, spending more than $10 billion (see chart) to evaluate its geologic suitability. And few are enthusiastic about restarting the bitter political arguments over where to put a repository. Sites in Washington state and Texas, which were under consideration until Nevada was controversially selected, might be options, as is an area in southeast New Mexico near the Department of Energy's Waste Isolation Pilot Plant, which stores military nuclear waste and where the local community has expressed interest in hosting a site.

Starting anew

The political challenges surrounding Yucca Mountain might prompt the Obama administration to take a fresh look at reprocessing: purifying plutonium-239 and uranium-235 and recycling those fuels to reduce the waste's mass and volume. Because the pure materials can be used in nuclear weapons, the US suspended reprocessing of spent fuel in 1977. The previous administration began a programme, the Global Nuclear Energy Partnership, to explore an international reprocessing project, but Congress gave the programme less than half the money that Bush requested. Under Obama, the project may stop altogether.

"Leaving it where it is, putting it centrally or reprocessing it can all be done. But in all cases, there has to be a final resting point for the solid waste," says Corradini. "It's pretty clear from an international perspective that geologic disposal of high-level waste, and probably of any nuclear waste, is the favoured option," adds John Garrick, chairman of the US Nuclear Waste Technical Review Board, based in Arlington, Virginia.

Some countries are well on their way towards siting a repository: Finland is working on a repository at Olkiluoto, which could be operational by 2020. Sweden is finalizing research on two candidate disposal sites and expects to choose one by the end of the year.

In both Finland and Sweden, the key to success was that governments adopted a cautious time schedule and a stepwise approach and involved the local community from the start, says Barbara Pastina, a nuclear-waste scientist at the Helsinki-based engineering firm Saanio and Riekkola Oy. In Finland, she says, "the whole nation was represented in the decision to build the repository" at Olkiluoto. The community had the right to veto the location at the beginning, and parliament voted on the decision. After early setbacks, Canada and the United Kingdom are also on track to find geologic repositories for long-term storage. Canada reorganized its national waste-management efforts in 2002 and is moving towards a siting phase, whereas the United Kingdom restarted in 2001.

ADVERTISEMENT

By contrast, powerful states' efforts to avoid hosting the repository have stymied US attempts to find a site. Senator Harry Reid (Democrat, Nevada), now the Senate majority leader, has fiercely opposed the project from the beginning, and many Nevadans are still fighting the Yucca Mountain proposal. "They've always felt that it was hoisted on them rather than them volunteering," says Todd Allen, an assistant professor of nuclear engineering at the University of Wisconsin.

Public consent has been the missing ingredient in Yucca Mountain from the beginning, agrees McCombie. The trick to finding another location, he says, is a "modern approach that combines good science with a consensus of enough people that it's the right thing to do". The United States hasn't built a nuclear power plant in three decades, but a resurgence of nuclear power is on the horizon. The NRC is considering licences for 26 new nuclear power plants, and construction could begin as early as 2012 — increasing the pressure on the country to solve long-term disposal once and for all. 