Introduction
Endosseous osseointegrated implants are now widely used to replace missing teeth and there is a great deal of evidence to support their efficacy.1, 2 Failures however do occur and although the most common cause is failure of integration, a less common cause is fracture of the body of the implant accounting for about 0.6% of failures.3
Case study
A 64-year-old female attended the surgery complaining of a loose and painful bridge at UR45 (14, 15). She gave a history of having an implant placed in this area about 2 years previously and more recently, 6 months ago, the crown at UR3 (13) had become de-cemented. After its re-cementation her bite had 'felt different'. Examination revealed an implant-retained cantilever bridge at UR45 (14,15) supported by a single implant at UR4 (14). The implant was a Brånemark Mark II (Nobel Biocare, Gothenburg, Sweden), regular platform (3.75 mm) fixture and was 18 mm in length. There was a post-retained crown at UR3 (13). Some redness and swelling in the soft tissues around the implant was evident and the bridge was mobile. Teeth present on examination were UL2347 (22–24, 27), UR123 (11–13) and LL12345 (31–35) and LR1234578 (41–45, 47, 48). Fixed bridges were present replacing UL1 (21) and UL56 (25, 26) with full crown retainers at UR1 (11), UL2 (22) and UL4 (24) and UL7 (27) respectively. LR6 (46) space was closed by drifting of LR78 (47, 48). All teeth present were symptom free.
A periapical radiograph (Fig. 1) revealed a fracture in the body of the implant at the position of the end of the prosthetic screw. The loose bridge was removed under local analgesia together with the implant fragment (Fig. 2) and a panoral radiograph was taken (Fig. 3).
A number of options were considered:
1. Removable partial denture
The patient did not want a removable solution therefore Option 1 was not considered further.
2. Restoration of remaining implant fragment
There was sufficient remaining implant (about 10 mm) and prosthetic screw hole to support a single tooth restoration. This would have involved the preparation of the fragment to provide a flat prosthetic table and the construction of a customised abutment. The likelihood of failure was considered to be too high and as the patient also wanted the space at UR5 (15) restoring this option was not considered further.
3. Removal of fragment and new implant placed at site
It was decided that the removal of the remaining implant fragment using a trephine would have resulted in considerable bone loss as a 4 mm trephine with external dimensions of 4.5 mm would have been used. It is likely that the placement of a second fixture at the same site would have required bone grafting to provide an adequate quantity of bone and this was not acceptable to the patient.
4. Removal of UR3 (13) and implants placed at UR3 (13) and UR5 (15)
This option was chosen as being most likely to provide a long-term stable solution that was acceptable to the patient. Two implants can be safely used to support a three-unit bridge to replace UR345 (13–15) and UR3 (13) was a failing post crown with a poor prognosis.
An immediate, temporary, removable partial denture was constructed to replace UR345 and UR3 was extracted. About 6 weeks later two implants were placed at UR3 and UR5 using the standard Brånemark protocol. They were both Brånemark implants being Mark IV TiUnite® implants of 15 mm and 11.5 mm lengths respectively. As the implant fragment was not visible a guide pin was screwed into the remaining implant fragment to mark its position during surgery (Fig. 4). A two-stage approach was to be used and therefore cover screws were placed and the wound closed. After 6 months the implants were exposed and healing abutments attached.
The remaining implant fragment was below the crest of the bone and so it is likely that the bone would remodel around this possibly covering it completely. The full thickness flap raised for the placement of the implants was closed over the site and as can be seen in Figure 5 healing was uneventful and complete.
Fixture head impressions were taken 2 months later and two Procera (Nobel Biocare, Gothenburg, Sweden) titanium custom abutments constructed. A 3-unit ceramo-metal bridge was constructed and cemented over these with a temporary cement (Improv, Nobel Biocare, Gothenburg, Sweden) (Figs 5, 6).
Discussion
Implant body fracture is a rare complication of implant treatment occurring in only about 0.6% of fixtures. An in vivo study analysing the mechanism of fracture of implants concluded that fatigue stress fracture occurs with repeated loading.4 In this case the re-cementation of the post crown at UR3 (13) may well have altered the occlusion causing excessive loading of the implant bridge resulting in a fatigue stress fracture. Rangert et al.5 found that partial bridges with cantilever designs accounted for 83% of implant fractures and that 90% of fractures occurred in the posterior regions. It has been shown in animal studies that crater-like bone loss will occur around implants with excessive dynamic loading6 and this loss of bone support will allow flexing of an implant under loading and possibly contribute to a fatigue stress fracture. In the past-prosthetic screw loosening sometimes leading to screw fracture has occurred7 when occlusal overload is present but improvements to screw designs, allowing higher preloads has made screw loosening much less common. However this may perhaps lead to failure elsewhere in the system such as fracture of the body of the implant. Such fractures can be difficult to manage as patients invariably expect a fixed solution and therefore will not accept a removable partial denture. Care must be taken during treatment planning to minimise the risk of implant body fracture by designing a prosthesis, which allows for axial loading where possible and a favourable distribution of occlusal forces. The avoidance of a cantilever design in partial cases, particularly in the posterior regions may well be advised. The periodontal ligament supporting a natural tooth will allow for movement of the tooth under loading and this will not occur when an implant is loaded as it is in direct apposition to bone, this may result in excessive loading of an implant in function and therefore must be avoided. Fracture of the body of an implant is a major cause of late failure3 which may well be avoidable with careful planning.